Introduction
The full opening of Mumbai’s coastal road, a significant infrastructure project, has been postponed to October. This delay is a major setback from the original deadline of May. The postponement highlights the complexities and challenges of this ambitious project, initially expected to be completed in 2022.
Project Overview
The Mumbai coastal road project is a massive undertaking with a budget of Rs 13,984 crore. Its primary goal is to improve connectivity and reduce traffic congestion along the city’s coastline. However, a leakage issue in the newly inaugurated stretch has forced the Brihanmumbai Municipal Corporation (BMC) to delay the full road opening by nearly two years from the initial projection.
Reasons for the Delay
Two main factors have contributed to this delay:
- Labor Shortage: Approximately 20% of the workforce, totaling around 6,500 workers, have returned to their native places. This seasonal occurrence in May has led to a shortage of skilled manpower.
- Monsoon Challenges: The upcoming monsoon season poses logistical difficulties. Critical construction activities, such as bitumen laying, are hindered by the heavy rains.
Current Progress
Despite these setbacks, the project is 89.2% complete. Significant progress has been made in road construction and interchanger works. However, the remaining tasks require favorable weather conditions for optimal execution.
Partial Opening Plans

BMC plans to open the northbound stretch of the road from Marine Drive to Haji Ali by June 10. After this, work will continue towards Worli. The project’s timeline has already undergone multiple revisions. Initially, the opening was deferred from November 2023 to March 2024 due to changes in navigation span requirements.
Changes in Project Specifications
The government’s decision to increase the navigation span to 120 meters, compared to the previously proposed 56 meters, has further contributed to the project’s timeline adjustments. This change was necessary to accommodate larger vessels and ensure safer navigation, but it also added complexity to the construction process.
Commitment to Completion
Despite these challenges, BMC remains committed to addressing the construction issues and completing the Mumbai coastal road. The project holds immense potential to improve traffic flow and enhance connectivity along Mumbai’s busy coastline. Its successful implementation will significantly impact the city’s infrastructure and promote economic growth.
More articles, CLICK HERE
Conclusion
The full operation of the Mumbai coastal road has been postponed to October due to construction challenges and a labor shortage. Despite these setbacks, significant progress has been made, and BMC plans to partially open the road soon. The project, once completed, will alleviate traffic congestion and boost connectivity, benefiting Mumbai’s infrastructure and economy.